TxDOT Weekly Update: Sept. 23-27

The Texas Department of Transportation continues construction and maintenance work on roadways in Abilene and surrounding areas for the upcoming week.
The Texas Department of Transportation continues construction and maintenance work on roadways in Abilene and surrounding areas for the upcoming week.
 
Abilene Area Office construction projects:
I-20 frontage roads from Pine Street to Loop 322: Crews continue work on frontage roads, turnarounds and ramps. Drivers should use caution and follow warning signs and traffic control devices.

Loop 322 from I-20 to the Waldrop Interchange: Crews are completing remaining paving work and will begin striping soon. Drivers should expect intermittent daytime lane and ramp closures.

Rainy Creek Bridge, E. US 80 east of Loop 322: Work to replace the bridge continues. Traffic is limited to one lane in each direction.
   
Upcoming project: Work to convert frontage roads from two-way to one-way operation on Loop 322 from Maple Street to Lytle Creek is expected to begin in October.

Taylor County Maintenance Office projects:

US 277 near FM 707 intersection: Level-up pavement.

FM 89 between Rebecca Lane and Robertson Drive: Silt removal, ditch cleaning and storm drain repair. Work will continue to FM 707 through November. Some lane closures will be necessary.